The production system records what the line made. The planning system records what the business believes it has. When a new material code is set up fully in one and only partly in the other, the planning system can reject every confirmation for orders that use it, into an error queue nobody is watching. The line shows output confirmed, the pallets are on the floor, and planning replans and expedites around stock it cannot see.
- Confirmed in the production system means recorded and sent. It does not mean posted in the planning system.
- The tell is an error queue where the rejections share one material code, next to inventory variance and expedites for the same items.
- Correcting the master data stops new rejections. The backlog still has to be reposted, in order, by someone who owns it.
Two records of the same pallet
A finished pallet is recorded twice. The operator confirms it in the production system, which tracks orders on the floor. That system then sends a confirmation to the planning system, which posts the finished goods into inventory, consumes the components and moves the order towards closed. Most days the two records agree so closely that people treat them as one.
They can drift apart in several ways: a cutover, an interface outage, a change to how units are counted. This post follows one of them. A new material code is introduced, perhaps a reformulated product or a new pack size. It is set up far enough for an order to be released and for the line to run it. What it lacks is something only posting needs: a unit conversion, a storage location or a valuation setting. Every confirmation for an order using that code is rejected on arrival.
The rejection is recorded properly, in the interface's error queue. The production system has already shown the operator a tick.
Why both systems look right
- The production system shows output confirmed against the order, with quantities and times.
- The interface is up and passing messages. Orders on established material codes post normally, so its overall success rate barely moves.
- The planning system shows the order as released and not yet delivered, which is a normal state for an order.
- The error queue holds the rejections, alongside the routine ones that are always there.
- Planning sees a shortage and does its job: it replans, and it expedites.
Nobody is looking at a fault. Planning is looking at an order that seems late, and the floor is looking at a job that seems finished.
Where it surfaces first
The first people to notice are not in IT. A dispatcher cannot pick stock that is standing in front of them. Customer service promises a later date for goods already made. A buyer expedites components for a repeat order that is not needed. Put together, the records tell one story:
- production confirmations sent, by order and material code
- posting errors in the interface queue, grouped by material code and error text
- inventory variance from cycle counts: finished goods found that the system does not hold, and components the system holds that have been used
- expedite orders and replanned production for the same materials
- warehouse notes such as “stock on floor, not in system”
Grouped by material code, the errors stop looking like background noise. They all start on the day the new code first ran.
A confirmation has two ends. The production system knows it was sent. Only the planning system knows whether it was posted. A tick on the sending side that does not wait for the answer describes the message, not the inventory.
What it costs, and how to size it
The unit of loss is expedite cost and inventory write-offs. For your own plant:
- Match confirmations sent against postings received since the new code was introduced. The unmatched ones are the gap, in units and in orders.
- List the expedites and extra production orders raised for those materials in the same window, and total their premium over normal cost.
- Add the stock adjustments and write-offs booked against those materials at count time.
- Add late or short shipments for goods that were physically available.
The first step needs two reports that already exist, each owned by a different team.
Why new codes keep doing this
Introducing a material touches engineering, production, planning, finance and the warehouse, and each sets up its own part. The launch checklist ends when the line can run the product. Whether the first confirmation posted is not on anyone's list. If this has happened before, the likely repair was to complete the master data and repost the backlog by hand, with the ticket closed as a data fix. The next new code meets the same checklist.
What fixes it
- Master data owner: complete the material setup in the planning system, and make that a gate before the first order is released.
- Integration team: report posting errors by material code and age, and send that report to someone who owns the queue.
- Production systems owner: show confirmed only when the planning system has acknowledged the posting, and show sent until then.
- Production control and finance: repost the backlog in sequence, then reverse the adjustments and expedites that are no longer needed.
- Any planning agent: an eval case its next release must pass. Before recommending an expedite, it checks for unposted confirmations on that material.
Where Traxivo fits
Traxivo reads production confirmations, interface errors, inventory counts and purchasing records through read-only connections to business systems, and stays outside control networks. It links them into one issue with a history, so the error queue, the variance and the expedites are read as one failure. It recognises when the next material launch repeats it, names the owners, and drafts the follow-up for a named person to approve. It does not repost anything; your teams do that. See unconfirmed production on the industrial page, and how the pattern looks in other industries.
The ten use cases on the Traxivo for Industrial page are the ones most manufacturing and industrial iot estates share. Your niche will have failures of its own. We build custom solutions for those on top of the same platform: connectors for the feeds only your niche has, detection for the pattern only your estate shows, and the loss counted in your own unit. The same approach extends to niches such as food and beverage batch plants, discrete assembly with vision inspection, temperature-controlled supply chains and connected equipment makers.
Sources
- Company filing with the US Securities and Exchange Commission. Tennant Company Reports 2025 Fourth-Quarter and Full-Year Results (Form 8-K, Exhibit 99.1), 2026.
- Company filing with the US Securities and Exchange Commission. Tennant Company Reports First Quarter 2026 Results (Form 8-K, Exhibit 99.1), 2026.
- Warranty Week. 23rd Annual Product Warranty Report, 2026.
Every figure on this page comes from the published source it is linked to and describes the industry at large. None is a Traxivo or customer result.
Frequently asked questions
Why would a planning system reject a production confirmation?
Because the order refers to something the planning system cannot post against. With a new material code, the cause can be incomplete setup: a missing unit conversion, storage location or valuation setting. The rejection is correct. The problem is that nobody sees it.
How do I check for unposted production without a new tool?
Compare two reports you already have: confirmations sent by the production system and postings received by the planning system, for the same orders and dates. Anything in the first and not the second is unposted. Group what you find by material code.
Does Traxivo repost the failed confirmations?
No. Traxivo reads through read-only connections, links the evidence into one issue, names the owners and drafts the follow-up for a named person to approve. Your teams correct the master data and repost.
Stop rediscovering the same integration failure
Traxivo links the alerts, tickets and email threads your teams already produce into one history per issue, recognises when a fault returns, and drafts the follow-up with the evidence attached. Nothing is sent until a person approves it.
See how Traxivo works See Traxivo for Industrial